HDB renovation timing: hours, noisy works and deadlines
Renovation Rules & process / 2026

HDB renovation timing: hours, noisy works and deadlines

a wall clock beside an HDB corridor door with a notice on it - HDB renovation timing

In this guide

Planning a renovation?

See the scope of our renovation services.

The short answer

HDB sets the hours a contractor may work in a flat, and shorter hours for noisy work. It also sets how long the whole job may take. The rules are the same for every block. Here they are in one place, with the source.

The hours

Type of workMonday to FridaySaturdaySunday and public holidays
General renovation9am to 6pm9am to 6pmNot allowed
Noisy works9am to 5pmNot allowedNot allowed

Noisy works are also not allowed on the eves of New Year’s Day, Chinese New Year, Deepavali, Hari Raya Puasa and Christmas Day.

Source: HDB, Important Information on Renovations

 

What counts as noisy

HDB’s examples: demolishing walls, removing wall or floor finishes, cutting tiles, and heavy or excessive drilling. Two more limits apply to this kind of work:

  • Demolishing walls and removing wall or floor finishes cannot take more than 3 consecutive days.
  • Only 2 handheld power tools of the type HDB approves may be used at any one time.

 

The notice to your neighbours

  • Neighbours within a radius of 2 units get a written notice at least 5 days before work starts, with the dates of the work.
  • This applies to works that do not need a permit as well, carpentry included.
  • HDB’s Notice of Renovation stays on display outside the flat until the work is finished.

HDB also suggests keeping the main door closed while work is going on, where possible, to cut the noise in the corridor.

 

How long the whole job may take

The clock starts on the date of the renovation permit.

BlockTime allowed
Newly completed block3 months
Existing block1 month
Window works only2 weeks

One month is short for a full resale renovation. It is why the order of work matters: hacking and wet works go first, and carpentry is built off site while the tiling is done. Our resale renovation sequence guide shows the order we follow.

 

DIY work

The contractor hours do not apply to your own small jobs. HDB asks owners to avoid DIY drilling and hammering between 10.30pm and 7am, and to tell neighbours first if that cannot be helped.

 

If you are the neighbour

Check the Notice of Renovation at the flat. It shows the dates the work is allowed. If work is going on outside the hours above, speak to the contractor or the person in charge first; their contact is on the Notice of Renovation at the door. If that does not settle it, contact HDB.

 

Why the hours matter to the owner

The owner is responsible for the renovation in the flat, not only the contractor. HDB says owners must make sure the contractor follows the permitted times. A listed contractor who breaches the rules can receive demerit points, and both owner and contractor can be fined on conviction.

Explore our HDB resale renovation service →

Send us your floor plan. WhatsApp +65 8700 1377 with the floor plan and a short brief. We reply Monday to Friday, 9am to 6pm, and quote line by line after a site visit.

Common questions

General work, yes, from 9am to 6pm. Noisy work such as hacking and tile cutting, no.

No. No renovation is allowed on Sundays or public holidays.

Heavy drilling by a contractor counts as noisy work and stops at 5pm on weekdays.

No. Condos follow the by-laws of their management corporation. Ask the management office for the renovation hours before you plan the schedule.

Not more than 3 consecutive days for demolishing walls and removing wall or floor finishes.

Planning a renovation?

See the scope of our renovation services.

Keep planning

HDB licensed contractor: how to check before you sign

The rule in one paragraph Under the Housing and Development (Renovation Control) Rules 2006, a…

Read guide

Permits

HDB renovation permit: what needs one, who applies, and when you can work

Which works need a permit Demolishing or hacking walls (non-structural only; structural slabs, beams and…

Read guide

Kitchens

Open kitchen conversion: what it takes in an HDB flat or condo

First check: is the wall structural? Structural walls, columns and beams cannot be removed in…

Read guide