The hours
| Type of work | Monday to Friday | Saturday | Sunday and public holidays |
|---|---|---|---|
| General renovation | 9am to 6pm | 9am to 6pm | Not allowed |
| Noisy works | 9am to 5pm | Not allowed | Not allowed |
Noisy works are also not allowed on the eves of New Year’s Day, Chinese New Year, Deepavali, Hari Raya Puasa and Christmas Day.
Source: HDB, Important Information on Renovations
What counts as noisy
HDB’s examples: demolishing walls, removing wall or floor finishes, cutting tiles, and heavy or excessive drilling. Two more limits apply to this kind of work:
- Demolishing walls and removing wall or floor finishes cannot take more than 3 consecutive days.
- Only 2 handheld power tools of the type HDB approves may be used at any one time.
The notice to your neighbours
- Neighbours within a radius of 2 units get a written notice at least 5 days before work starts, with the dates of the work.
- This applies to works that do not need a permit as well, carpentry included.
- HDB’s Notice of Renovation stays on display outside the flat until the work is finished.
HDB also suggests keeping the main door closed while work is going on, where possible, to cut the noise in the corridor.
How long the whole job may take
The clock starts on the date of the renovation permit.
| Block | Time allowed |
|---|---|
| Newly completed block | 3 months |
| Existing block | 1 month |
| Window works only | 2 weeks |
One month is short for a full resale renovation. It is why the order of work matters: hacking and wet works go first, and carpentry is built off site while the tiling is done. Our resale renovation sequence guide shows the order we follow.
DIY work
The contractor hours do not apply to your own small jobs. HDB asks owners to avoid DIY drilling and hammering between 10.30pm and 7am, and to tell neighbours first if that cannot be helped.
If you are the neighbour
Check the Notice of Renovation at the flat. It shows the dates the work is allowed. If work is going on outside the hours above, speak to the contractor or the person in charge first; their contact is on the Notice of Renovation at the door. If that does not settle it, contact HDB.
Why the hours matter to the owner
The owner is responsible for the renovation in the flat, not only the contractor. HDB says owners must make sure the contractor follows the permitted times. A listed contractor who breaches the rules can receive demerit points, and both owner and contractor can be fined on conviction.