HDB renovation permit: what needs one, who applies, and when you can work
Renovation Rules & process / 2026

HDB renovation permit: what needs one, who applies, and when you can work

Illustration - HDB floor plan, tape measure and tile samples in an empty flat

In this guide

Planning a renovation?

See the scope of our renovation services.

The short answer

In an HDB flat, the contractor applies for the permit, not you, and only a contractor listed in HDB’s Directory of Renovation Contractors may do so. Hacking, floor replacement, bathroom works and window works need one. Noisy works are limited to weekday daytime and three consecutive days. New flats have a three-year wait before bathroom finishes can be hacked.

Which works need a permit

  • Demolishing or hacking walls (non-structural only; structural slabs, beams and load-bearing walls cannot be altered at all)
  • Replacing floor finishes, including hacking existing tiles
  • Bathroom and toilet works, including replacing floor and wall finishes
  • Window replacement and some air-conditioner installations
  • Certain plumbing and sanitary changes

Painting, carpentry, replacing cabinets, light fittings and most cosmetic work do not need a permit. If in doubt, ask us; we check before quoting.

 

Who applies

Only contractors listed in HDB’s Directory of Renovation Contractors can submit the application, which is done electronically. Innovation Workshop is listed as HB-01-3459G. If a contractor asks you to apply yourself, or cannot show a directory number, stop.

Explore our HDB resale renovation service →

 

The permit window

Permitted works must be completed within one month of the permit date in existing blocks, and within three months in newly completed blocks. That window shapes the sequence: hacking and wet works first and fast, carpentry fabricated in parallel so installation does not wait.

 

Working hours

Type of workAllowed
General works: plastering, painting, screeding, carpentry installation9am to 6pm, Monday to Saturday
Noisy works: demolishing walls, removing floor and wall finishes, cutting tiles, heavy drilling9am to 5pm, Monday to Friday, and completed within 3 consecutive days
Sundays and public holidaysNo renovation works

 

The three-year rule for new flats

In newly built flats, the wall and floor finishes in bathrooms and toilets cannot be removed for the first three years from the block’s completion date, to protect the waterproofing. During that period bathrooms can still be refreshed by overlaying tiles and changing fittings. Enlarging a bathroom is also only permitted after the three years, within HDB’s size limits.

 

What happens if you skip the permit

HDB can require the flat to be restored to its original condition at the owner’s cost, and the contractor can be removed from the directory. It is not worth it, and no listed contractor will do it.

Send us your floor plan. WhatsApp +65 8700 1377 with the floor plan and a short brief. We reply Monday to Friday, 9am to 6pm, and quote line by line after a site visit.

Common questions

Submission is electronic and straightforward works are typically approved within days; we build it into the schedule.

General works, yes, 9am to 6pm. Noisy works no.

Yes, the three-year restriction has passed, subject to the permit.

Planning a renovation?

See the scope of our renovation services.

Keep planning

Kitchens

Open kitchen conversion: what it takes in an HDB flat or condo

First check: is the wall structural? Structural walls, columns and beams cannot be removed in…